HYDRO-ELECTRIC/
IRRIGATION PROJECT
OWNER STATUS DETAILS OF THE PROJECTS
      Capacity
(MW)
Barrage (B)/Dam(D) (Nos.) Power Houses (Nos.) Underground Excavation (Lac Cum) Concrete (Lac Cum) Tunneling in Underground Works (km)
A) COMMISSIONED & IN OPERATION                
- 'BUILD-OWN-OPERATE' JAL                
1) Baspa (Stage-II)in Himachal Pradesh JHPL Commissioned in June-2003 300 1 (B) 1 4.00 3.20 12.10
- JAL's CONTRACTS ON EPC*                
2) Chamera-II in Himachal Pradesh NHPC Commissioned in June-2004 300 1 (D) 1 13.70 4.50 20.60
Sub Total (A) COMMISSIONED & IN OPERATION     600 1 (B) + 1(D) 2 17.70 7.70 32.70
B) UNDER EXECUTION                
- 'BUILD-OWN-OPERATE' by JAL                
3) Vishnu-Prayag in Uttaranchal JPVL Commissioning scheduled in 2006 400 1 (B) 1 7.40 2.70 24.50
4) Karcham-Wangtoo in Himachal Pradesh JKHCL Commissioning scheduled in 2011 1,000 1 (D) 1 41.42 13.18 30.00
- JAL's CONTRACTS ON EPC*                
5) Baglihar (Stage-I & II) in J&K JKSPDC Commissioning scheduled in 2006 (Stage-I Works) & 2007 (Stage-II Works) 900 1(D) 2 18.45 25.59 10.10
6) Omkareshwar in Madhya Pradesh NHDC Commissioning scheduled in 2007 520 1(D) 1** - 14.20 -
7) Alimineti Madhva Reddy in Andhra Pradesh Govt. of AP To be completed in 2010 - - - 40.36 7.07 50.75
Sub Total (B) UNDER EXECUTION     2,820 1(B) +3(D) 5 107.63 62.74 115.35
Grand Total ('A' + 'B')     3,420 2 (B) + 4(D) 7 125.33 70.44 148.05