JAIPRAKASH INDUSTRIES LIMITED
WORK IN HAND AS ON 30.09.2003

S.No. Name of the Proejct Face value of work completed upto 30.09.2003 Total value of work completed up to 30.09.2003 including escatation and extra items Estimated Value of balance work including escalation and extra items Estimated Completion date
(1) (2) (3) (4) (5) (6)
10

Teesta (Stage-V) Hydroelectric Project, Sikkim

       
 

a) Construction of Coffer Dams, Concrete Dam, Intake, Desilting Chamber and part Head Race Tunnel

145 152 268 November, 2005
 

b) Construction of Power House, Surge Shaft, Pressure Shafts and part Head Race Tunnel

92 97 121 September, 2005
11

Conversion of Delhi-Gurgaon Section of NH-8 into an access Controlled 8/6 lane highway from Km. 14.30 to Km. 27.70.

NIL NIL 178 July, 2005
12

All Civil and Hydromechanical works of 450 MW Baglihar Hydroelectric Project (Stage-II), Jammu & Kashmir.

NIL NIl 824 50 months fro effective date of start (work yet to start)
13

All Civil and Hydromechanical works of 520 MW Omkareshwar, Hydroelectric Project, Madhya Pradesh

NIL NIL 931 48 months from effective date of start (work yet to start)
14

All Civil Hydromechanical and Electromechanical works of 1000 MW Karcham Wangtoo Hydroelectric Project, Himachal Pradesh.

NIL NIL 3,278 72 months fro effective date of start (work yet to start)
  Total 5,666 7,660 9,237  