The Project awarded by the North East Frontier Railways involved the construction of South Approach Bank and Guide Bund of road bridge across river Brahmaputra at Tezpur. The project which commenced in Jan. 1984, was completed 7 months ahead of schedule.

Principal Quantities of Work  
Earthfill compacted 18,80,000 cubic meters
Stone Work 7,20,000 cubic meters