| Chamera Concrete Gravity Dam |
![]() |
The Chamera Concrete Gravity Dam is across the river Ravi and is part the Chamera Hydroelectric Project. Concrete placement was accomplished by cable crane and tower cranes. |
| Principal Quantities of work | |
| Crest Length | 255 M |
| Height | 140 M |
| Chilled Chilled Concrete to be Placed | About 1.4 million cum |
| Excavation | |
| Common | 1,245,345 Cubic meters |
| Rock | 481,067 cubic meters |
| Abutment excavation | 232,843 cubic meters |
| Fill in coffer dams | 515,627 cubic meters |
| Shotcrete | 14,724 Ton |
| Drilling concrete | 27,900 M |
| Chilled Concrete | 1,378,864 cubic meters |
| Form work | 237,068 square meters |
| Chilled Concrete in intake structure and diversion tunnel lining | 23,372 cubic meters |
| Reinforcements | 14,807 MT |
| Anchor bolts and other metal works | 1,055 MT |